Pat Wiltshire, chair of the Water Quality Improvement Committee, reported to the membership on the status of this project. Highlights of his report are listed below.

A LARE grant was awarded to OMLCIA for a maximum of $120,000.

The contract with Superior Seawall, Docks, and Dredging (Illinois) is for $76,900. The OMLCIA required match is $15,380.

Approximately 5,000 cubic yards of organic material and sediment will be removed hydraulically.

The project is 75% complete. An additional 10-12 days of work will resume after July 4.

The sediment dewatering basin will be removed in November. Any necessary landscape remediation will also be completed at that time.

The county surveyor plans to clean out the Dove Creek sediment traps in 2017 after money from the ditch tax collections becomes available.

News & Events AUG 25th

To treat or not to treat?

That’s a good question 

Read More Read ALL

Local News NOV 15th

Mexican executed for family slayings

HUNTSVILLE, Texas – A Mexican citizen on death row in Texas was executed Wednesday night for the sledgehammer killings of his wife and two children more than 26 years ago....

Read More